S. No. |
Project Name |
Clients |
Cable Laid
(km) |
Location |
Starting Date |
Completed. Date |
Description of Work |
|
1 |
Ministry of Defense & Aviation - Fiber Optic Cable Laying Direct
Buried |
MODA |
800 |
Eastern Region
(Dammam
to Jubail, KKMC,
Haf’r Al-Batin) |
7/11/1411H |
5/3/1414H |
Inst. of direct buried FO cable, including Thrust boring works, under
Aramco pipeline / highway crossings, road bridge/wadi crossings at
various locations in 800 kms. Length. Inst. of Manholes, Hand holes,
with splicing, testing, and commissioning. |
|
2 |
450-K Project |
STC |
205 |
Taif |
20/2/02 |
20/7/03 |
Laying of FO Cable Network of cable size 96 & 36 Fiber, connecting
various Exch. with RAN, including all types of Civil works, Inst. of
Electronic Cabinets, Laying of Sub-duct & mini-duct, Splicing, Testing
& Termination, Installation of ODF, etc. complete |
|
3 |
450-K Project |
STC |
70 |
Taif |
10/7/02 |
10/3/03 |
-- as above -- |
|
4 |
Royal Saudi Air Force - Fiber Optic Cable Laying (Direct Buried) |
RSAF |
180 |
Eastern Region |
4/11/1410H |
15/12/1411H |
Inst. of direct buried FO cable, including FO pulling in existing
duct, passing ARAMCO pipes at various locations. Used existing
Manholes, Hand holes, with splicing, testing and commissioning. |
|
5 |
TEP
450K
Job
No.:- 1542141-
Pulling & Jointing FO Cable from Exchange 403 to YRC1 & YRC2 |
Saudi Telecom Co |
45.94 |
Yanbu |
27/10/01 |
9/1/02 |
Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a
sub-duct. Jointing, termination, testing & commissioning. |
|
6 |
TEP-450K
Hawi Exchange.
Job
No. 34-565 |
Saudi Telecom Co |
11.22 |
Taif |
24/2/03 |
18/3/03 |
-- as above -- |
|
7 |
TEP-550K (FON) –
Job
No.: - 1433-204 |
Saudi Telecom Co |
32.00 |
Jubail |
20/12/00 |
8/4/01 |
Operation of continuous well point system, Aramco pipeline crossing
done manually. Thrust boring works at various locations. Pulling FO
cable, jointing, termination, testing & commissioning. |
|
8 |
TEP-550K Job No.:- 1542136-Pulling & Jointing FO Cable from Exchange
403 to three Electronic Cabinets. |
Saudi Telecom Co |
10.50 |
Yanbu |
16/4/01 |
27/4/01 |
Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a
sub-duct. Jointing, termination, testing & commissioning. |
|
9 |
TEP
Key Account – Job No:- 1433-232 |
Saudi Telecom Co |
6.50 |
Jubail |
25/9/01 |
27/10/01 |
Installation of FOC from Musanidah Exchange to Royal Commission Bldg.
& Jubail Industrial College & Petrochemicals Co. |
|
10 |
TEP-450K -DAKHNA ABDALIYA |
Saudi Telecom Co |
6.00 |
Qassim |
19/12/02 |
10/2/03 |
Inst. of PVC duct & sub-ducts in a duct. Pull FO cable in a sub-duct.
Jointing, termination, testing & commissioning. |
|
11 |
MODA Maintenance-Khamis Airbase |
Saudi Ericsson |
5.30 |
Khamis
Mushayat |
10/1/98 |
20/2/98 |
Laying of new Direct Buried cable & removing the old cable. |
|
12 |
STC
Job – 7511183 |
Saudi Ericsson |
4.70 |
Riyadh |
15/7/98 |
30/8/98 |
FOC UMUX1100 & mini Link installation |
|
13 |
HALAQAH (TCEN) Job No.:- A122 /A078 |
Saudi Telecom Co |
4.10 |
Taif |
1/7/01 |
9/9/01 |
Inst. of 4Way 32mm sub duct, Instl. Of FOC, splicing & Termination of
cable in ODF. |
|
14 |
SUHAILI (TIFS) Job No.:- A122 /A079 |
Saudi Telecom Co |
3.20 |
Taif |
6/7/01 |
10/8/01 |
-- as above -- |
|
15 |
TEP-450K, RAN 1/2/3 Job No.:- 3427428 |
Saudi Telecom Co. |
3.27 |
Jizan |
5/4/01 |
30/5/01 |
Supply & Inst. of 3 sub duct in empty sub duct |
|
16 |
MODA Maintenance-Taif Airbase - Laying of new Direct Buried cable &
removing the old cable. |
Saudi Ericsson |
2.85 |
Taif |
5/1/98 |
6/2/98 |
Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a
sub-duct. Jointing, termination, testing & commissioning. |
|
17 |
TEP-450K- Al-SANAIYA AR-RASS |
Saudi Telecom Co |
2.50 |
Qassim |
13/4/02 |
5/6/02 |
-- as above -- |
|
18 |
TEP-450K- Al-JANDAL AR-RASS |
Saudi Telecom Co |
2.50 |
Qassim |
7/12/02 |
7/2/03 |
-- as above -- |
|
19 |
TEP-550K, RAN 1/2/3
Job
No.:- 3427428 |
Saudi Telecom Co |
2.40 |
Jizan |
1/8/01 |
27/8/01 |
-- as above -- |
|
20 |
Job
No.- TKSP/625 |
Saudi Ericsson |
2.27 |
Eskan Village (Riyadh) |
2/4/00 |
25/4/00 |
-- as above -- |
|
21 |
TEP-450K Al-MEHFAL
AR-RASS
|
Saudi Telecom Co |
2.00 |
Qassim |
13/4/02 |
6/5/02 |
-- as above -- |
|
22 |
TEP-550K -SANAIYA (TIFS) Job No.:- 4423833 |
Saudi Telecom Co |
1.20 |
Taif |
5/9/01 |
16/11/01 |
Inst. of 4Way 32mm sub duct, Instl. of FOC, splicing & Termination of
cable in ODF. |
|
23 |
MODA Maintenance -Laying of new Direct Buried cable & removing the old
cable. |
Saudi Ericsson |
1.20 |
Qatif |
2/7/00 |
20/7/00 |
Excavation for laying of new FO cable beside existing FO cable &
removing old cable |
|
24 |
TEP-450K-DAKHNA ROAD |
Saudi Telecom Co |
1.00 |
Qassim |
27/12/02 |
23/2/03 |
Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a
sub-duct. Jointing, termination, testing & commissioning. |
|
25 |
MODA Maintenance -Direct Buried FO cable |
Saudi Ericsson |
0.60 |
Artawiyah Camp |
1/6/00 |
14/6/00 |
Inst. of 2-way duct & Marker Post |
|
26 |
MODA Maintenance -Laying of new Direct Buried cable & removing the old
cable. |
Saudi Ericsson |
0.40 |
Dilam |
1/9/00 |
14/9/00 |
Excavation for laying of new FO cable beside existing FO cable &
removing old cable |
|
27 |
TEP-450K,
Job
No.:- 3425529 |
Saudi Telecom Co |
7.08 |
Al-Baha |
14/1/1422H |
17/5/1422H |
Supply & Inst. of 50mm polythelene pipe, Install FOC-Group (1-3) in
50mm Polythelene pipe |
|
28 |
TEP-450K,
Job
No.:- |
Saudi Telecom Co |
4.05 |
Al-Baha |
2/9/01 |
8/10/01 |
Supp & Inst. of 4 standard sub ducts in main duct, Inst. FOC- Group
(1-3) in sub duct, Inst. of handholes |
|
29 |
TEP-450K,
Job
No.:- 3425530 |
Saudi Telecom Co |
3.31 |
Al-Baha |
9/6/01 |
4/10/01 |
Supp & Inst. of 4 standard sub ducts in main duct, Inst FOC- Group
(1-3) in sub duct. |
|
30 |
TEP-450K,
Job
No.:- 6425388, 6425339 |
Saudi Telecom Co |
2.63 |
Al-Baha |
1/7/01 |
6/9/01 |
-- as above -- |
|
31 |
SEC-CRB 510/19/3 |
Al-Sharif
KEC |
- |
Riyadh |
Apr. 2003 |
- |
Splicing, Termination & Testing of OPGW & UGFOC for 253km. Network |
|
32 |
TEP-OSP,
Project No.-224047(100m)
|
Saudi Telecom Co |
Copper |
Kingdom wide |
13/7/1424H |
- |
Inst. of FO cable and copper cables, M/holes, H/holes Inst. of PVC
duct & sub-ducts in a duct. Jointing, termination, testing &
commissioning. |
|
33 |
TEP-OSP,
Project No.- 224041(Junction)
|
Saudi Telecom Co |
68 |
Kingdom wide |
23/7/1424H |
- |
-- as above -- |
|
34 |
OSP
Network 450-K |
Saudi Telecom Co |
Copper |
Kingdom wide |
5/7/1422 H |
19/7/1424 H |
Excavation as per MOC & MOMRA requirements, Inst. of MHs / HHs,
Construction of different ways of Ducts encased in Concrete,
Mandrilling, Pulling cable (Copper & Fiber) in ducts and sub ducts,
Inst. diff. types of Cross connection Cabinets, Pedestals with
terminal blocks, Installation of different sizes of MDF & ODF in
Exchanges, Inst. of MDF terminal blocks & termination of ODF.
Including Splicing, Termination & Testing of Copper & Fiber cables
with Documentation, preparation of As built Drawings, Commissioning,
Preliminary Acceptance Test (PAT) & Handing over of Projects |
|
35 |
OSP
Network 550-K |
Saudi Telecom Co |
Copper |
Kingdom wide |
30/10/1420 H |
25/7/1422 H |
-- as-above -- |
|
36 |
SEC-CRB 504/22/3 |
Rajab & Silsilah / L.G / SST |
- |
Howta Suddair |
29-Nov-03 |
- |
Drum Testing, Splicing, Termination, Testing, Documentation &
Commissioning. |
|
37 |
SEC-CRB 523/22/3 |
Rajab & Silsilah / L.G / SST |
- |
Hail |
29-Nov-03 |
16-Feb-04 |
Drum Testing, Splicing, Termination, Testing, Documentation &
Commissioning, successfully completed and handed over to SEC-CRB in
presence of SEC-Representatives, LG & SST Representatives for
Commissioning. |
|
38 |
SEC-CRB 38/20/21 |
Kadi Trad. & Cont |
- |
Qassim |
26-Dec-03 |
April 2005 |
Drum Testing, Splicing, Termination, Testing, Documentation &
Commissioning. |
|
39 |
SEC-CRB 513/20/3 |
ATECON |
- |
Riyadh |
Nov.-03 |
Nov.-03 |
Diversion of working Fiber (OPGW-NFOC) for SEC-CRB for SEC-CRB of S/s
808. Within the limit of shutdown time of SEC i.e. 2 hrs. with
complete testing, Documentation & Commissioning. |
|
40 |
Civil Works for OSP Network. Contract No. 0215442 |
Saudi Telecom Co |
78.0
|
Tabuk
Hafr Al-Batin
Abha
Al-Baha
Najran |
July-04 |
- |
Laying of FO Cable Network of cable, connecting various Exch. with
RAN, Axis of Saudi Electricity Co. till RAN, including all types of
Civil works, Inst. of Electronic Cabinets, Laying of Sub-duct &
mini-duct, Splicing, Testing & Termination, Installation of ODF, etc.
complete |
|
41 |
OSP / PDS Cabling System at 4th Operating Area
CN : 30331021/00 |
SEC-EOA |
24 Core ADSS Cable (SM) G652B 4.5 Km
12 & 24 Core (MM) G652 14 Km |
AL-Jouf, Tabarjal , Qurayat, Rafha, AL-Uwaiqillah, Ar-Ar, Turraif,
Domat AL-Jandal Power Plant & Administration Buildings. |
July-04 |
June-06 |
This project provides Survey, Design & Installation of Outside /
Inside Plant Telephone and Fiber Optic Cables & its associated Hand
holes / Manholes and conduit system, Terminal Blocks, Joint Boxes,
Protectors, Splices, Racking, Hardware and Grounding system.
This new cable Installation is required at several Power Plant, Local
offices, and Work Centers to replace old and deteriorating Cables and
or to increase the existing capacity. New cable route are also
required to provide access to existing or proposed Fiber Optic /
Carrier Systems. This Contract is LSTK Basis. |
|
42 |
MODA Frequency Replacement Project, LDN-FON Route Najran -
Sultana |
Saudi Telecom Co |
FOC 36/10/125 Duct Type & Direct Burrial Type (208.616 Km) |
Najran-Fahad-Arisa-Sultana-Husainiyah |
Aug-05 |
Oct-05 |
A
complete LDN project surveyed, planned, designed and in progress of
implementation. It includes Cable installation by mole plough, Cable
installation in Duct, Splicing, Termination of Cable in ODF and many
related activity to various STC Exchanges, GSM, WLL. |
|
43 |
Ministry of Education - Jeddah |
Ministry of Education |
Construction of 3 Schools Buildings, in Jeddah. |
Ministry of Education |
28-10-1424H |
20-6-1426H |
Construction of 3 Schools Buildings, in Jeddah. |
|
44 |
Ministry of Education - Taif |
Ministry of Education |
Construction of 5 Schools Buildings in Taif City. |
Ministry of Education |
29-10-1425H |
10-6-1427H |
Construction of 5 Schools Buildings in Taif City. |
|
45 |
Institute of Technical Industries - Jizan |
Institute of Technical Industries |
Construction of Work Shop and Main Buildings Sabya, Jizan. |
Institute of Technical Industries |
6-11-1425 |
5-2-1427 |
Construction of Work Shop and Main Buildings Sabya, Jizan. |
|
46 |
H.H. King Abdullah
Project
|
King Abdullah Bin Abdul-Aziz Foundation |
King Abdullah Bin Abdul-Aziz Foundation for Developmental Housing
Dedicated to His Parents General Secretary Head Quarters |
Riyadh |
24-12-2005G |
06-08-2006G |
Skelton for Main Building (Concrete & Block) area 8,000 Sq.m 3 floor. |
|
47 |
Operation and Maintanance Directorate - MODA – Wadi Dawasir |
MODA |
Construction of Royal Hall, Accommodation & Warehouse |
Wadi Dawasir |
2-6-2003 |
2-6-2004 |
Construction of Royal Hall, Accommodation & Warehouse |
|
48 |
General Directorate of Military Works - MODA – Khamish Mushayat |
GDMW – MODA |
Turnkey Building Construction OF Various Buildings appr. Area 42,000
sq.m. . |
Khamish Mushayat |
1-5-1420H |
16-4-1425H |
Turnkey Building Construction.
|
|
49 |
GDMW
MODA – Najran |
GDMW -
MODA |
Turnkey Building Construction. |
Najran |
1-7-1423 |
3-12-1423 |
Turnkey Building Construction. |
|
50 |
STC-Jizan |
STC-Jizan
CN: 2022670 |
- |
Jizan |
March-2007 |
- |
Design & Engineering of FOC laying of FOC Installation MSAN Cabinets,
Splicing, Testing Commissioning, Laying of Copper Cables, Placing of
MH's/HH's, PE duct jointing, Testing & Commissioning. |
|
51 |
STC-Taif |
STC-Taif
CN: 2022670 |
- |
Taif |
March-2007 |
- |
Design & Engineering of FOC laying of FOC Installation MSAN Cabinets,
Splicing, Testing Commissioning, Laying of Copper Cables, Placing of
MH's/HH's, PE duct jointing, Testing & Commissioning. |
|
52 |
Patriot battalion to C3
network link RSADF, Khamis |
RSADF |
- |
Khamis, Mushayat |
July 06 |
July 07 |
Site Survey Engineering & Design. Installation of D/B F.O.C of 16 & 8
Core SM in between different air bases on LSTK-project. |