S. No. |
Client |
Project Manager |
Description of Work |
Reference |
Duration |
|
Start |
Complete |
|
1.
|
Ministry of Education – Al-Jouf |
Eng’r. Jalal Hamuda |
Construction of Main Administration Building at Sakaka Al-Jouf. |
Ministry of Education |
15-1-1426H |
14-6-1428H |
|
2.
|
Ministry of Justic-Al-Jouf |
Eng’r. Hany Hamza Hanoura |
Construction main Administration building of Justic Ministry,
Sakaka, Al-Jouf. |
Ministry of Justice |
20-3 1426 |
19-3-1429 |
|
3.
|
GDMW-MODA |
Eng’r. Mati Qaudri |
Construction of Three Schools Buildings at KKMC, Hafar Al-Batin. |
GDMW-MODA |
11-3-1427H |
10-9-1429H |
|
4.
|
SEC-COA |
Eng’r. Moin Uddin Shaikh |
Laying of FOC Cable from Al-Qassim Power Plant to Medina
Munawarah for a Distance of 500Km including Telecom Repeater
Shelters Splicing, Terminate & Testing. |
Underground Fiber Optic
Cable
Link.
Contract # 10531176/00 |
23-4-2006G |
22-10-2007G |
|
5.
|
Red Crescent
Project
|
Eng’r. Ahmed Kamal |
Main Building Consists Of Basement + 3 floor (7000 Sq.m) + Site
work + Water Tank + Utility. |
Ministry of Finance |
05-03-1427H |
05-09-1428H |
|
6.
|
Technical College Qassim
|
Eng’r. Abdul Karim |
Consist of 18 Building (24000 Sq.m) different types offices
building & workshop for training & site work (12,000 Sq.m) with
land scope. |
General Establishment for Technical Education & Training. |
May, 2007 |
Feb, 2009 |
|
7.
|
OSP/PDS upgrading of Cabling System West Operating Area
CN: 20561101/00 |
Eng’r. Tasawar E. Qureshi |
Installation of Outside/Inside plant telephone & F.O Cable, PDS
System Local Area Network (PDS-LAN) & its associated equipment. |
Different Location of Western Operating Area |
June-2006 |
Dec.-2008 |
|
8.
|
SEC-COA |
Eng’r. Moin Uddin Shaikh |
Supply & Laying of FOC Cable from Ruwaydah 8605 S/S (COA)-Al
Muwyah 110/33KV S/S (WOA) for a Distance of 360Km including
Splicing, Terminate & Testing. |
Underground Fiber Optic Cable Link.
Contract # 10631150/00 |
Dec-07 |
Dec-08 |
|
9.
|
Al-Zakry |
Eng'r. Nurul Alam |
Consist of 100 Residential Villas (17000 Sq.m) different types
in Yanbu. |
ZAKRY GROUP |
2-2-2007 |
1-2-2009 |
|
10.
|
Building
T10 & T11
Al-Qasr, Riyadh
Dar-Al-Arkan |
Eng’r. Hany Hamza Hanoura |
Consist of 2 Building (46000 Sq.m) different types Residential
building. |
Dar-Al-Arkan Real Estate Co. (Turner) |
March-2007 |
May-2008 |
|
11.
|
ARAMCO Gulf Operations |
Mohd. Shoaib Ashraf |
FIBER OPTIC CABLE CONNECTIVITY BETWEEN GATHERING STATION AND ALL
FLOW STATIONS ( Y1, Y2, Y3, Y4 ) |
Contract No. BT 649 IT07 |
August, 2007 |
January, 2008 |
|
12.
|
STC-Jizan
CN: 2032512 |
Eng'r. Ibrahim Ghulam |
Design & Engineering of FOC laying of FOC Installation MSAN
Cabinets, Splicing, Testing Commissioning, Laying of Copper
Cables, Placing of MH's/HH's, PE duct jointing, Testing &
Commissioning. |
STC-Jizan
CN: 2032512 |
April, 2007 |
- |
|
13.
|
STC-Taif
CN: 2032512 |
Irfan Najam Najmul Ghani |
Design & Engineering of FOC laying of FOC Installation MSAN
Cabinets, Splicing, Testing Commissioning, Laying of Copper
Cables, Placing of MH's/HH's, PE duct jointing, Testing &
Commissioning. |
STC-Taif
CN: 2032512 |
April, 2007 |
- |
|
14.
|
STC-Al-Baha
CN: 2032512 |
Mr. Naeem Khadin |
Design & Engineering of FOC laying of FOC Installation MSAN
Cabinets, Splicing, Testing Commissioning, Laying of Copper
Cables, Placing of MH's/HH's, PE duct jointing, Testing &
Commissioning. |
STC-Al-Baha
CN: 2032512 |
April, 2007 |
- |
|
15.
|
STC-Yanbu
CN: 2032512 |
Eng'r. Zahir Alam Sarker |
Design & Engineering of FOC laying of FOC Installation MSAN
Cabinets, Splicing, Testing Commissioning, Laying of Copper
Cables, Placing of MH's/HH's, PE duct jointing, Testing &
Commissioning. |
STC-Yanbu
CN: 2032512 |
April, 2007 |
- |